Skip Ribbon Commands
Skip to main content
SharePoint

Holding a Process at a Join until all Parent Activities are Complete

To insert a Join Path activity and hold the process at a point until all parent activities are complete, complete the following steps:

  1. Check out and open the process.

  2. In the Toolbox pane, click BPM. A list of activities is displayed.

  3. Double-click or drag the Join Path activity into the process.

  4. Link the activity appropriately with other activities.

  5. Right-click the Join Path activity. A shortcut menu is displayed.

  6. Select View Properties. The Join or Split Path window is displayed.

  7. Click the Join Behavior tab. The Wait Options are displayed.

  8. In the Wait Options section, select the Wait on all predecessor activities to complete option.

  9. Click OK. You configured a Join Path activity to hold a process until all parent activities are complete.
Related Topics
Holding a Process at a Join until a Parent Activity Completes
Holding a Process at a Join until specific Parent Activities are Complete
Create Rule for use in a Join Path Activity to Check if Branches Completed

Source
BPM Designer Topics > Overview of Activities and Activity Topics > BPM Activities > Join Path
Last modified at 7/31/2020 11:37 AM