To set a task to be due on a specific date and time, complete the following steps:
  1. From the Solution Explorer, check out the assignment profile.

  2. Open the assignment profile.

  3. Click the Due Date tab. The Due Date, Escalations, and Overdue action options are displayed.

  4. Select the Due Date check box. The Due Date fields are enabled.

  5. Select Due on. The Due on field is enabled.

  6. In the Due on field, select an editor and set the field to a static or dynamic value that indicates the date and time you want the task to be due. 

    Note:
    The value at runtime should be in one of the following format: M/D/YYYY H:MM:SS AM/PM (Example: 6/24/2010 5:00:00 PM)


  7. Click the save button. You set this task to be due on a specific date and time.
Related Topics
Setting a Task to be Due after a Specific Duration
Setting a Task to Escalate a User
Setting a Task to Ecalate to a User Group
Setting a Task to Escalate to a User Queue
Setting a Task to Escalate to a User in an Organization Chart  

Source
BPM Designer Topics > Overview of Solution Items and Solution Item Topics > Assignment Profiles
Last modified at 7/31/2020 11:58 AM